State wdt_ID Treatment Service Life Pavement Life Extension Lane Miles Completed (2016) Cost Per Square Yard (2016) Cost Per Lane Mile (2016) Total Project Cost Per Lane Mile Total Quantity Completed by Agency in 2016 (Tons/SY) Treatment Placed by Agency or Contract Specific Treatment Details (gradation, binder type, # of courses, etc.) Pavement Conditions Treated
Minnesota 6 150.287 3.54 24,921 31,659 Contract
Illinois 7 5-7 3 73.5 3.25 22,903.47 53,513.62 546,971 Contract Single Pass
North Dakota 8 7-10 497 75,000 Contract Rutting
Iowa 9 5 4 179 13,900 23,200 1,258,000 Contract Single and two course treatments Rutting, oxidized pavement, or low friction
Kansas 10 47 31,380 514,500 Contract 25 lb (one lift) or 35 lb (two lift) micro
South Dakota 11 8 6 60 20,100 25,000 528,100 Contract See SDDOT Special Provision for Microsurfacing Rutting
Michigan 12 3-6 3-6 2.5 45.50 Contract Binder: CSS-1hM and CSS-1mM
Indiana 13 8 8 10 100,270 Contract