Cold-in-Place Recycling

Statewdt_IDTreatment Service LifePavement Life ExtensionLane Miles Completed (2016)Cost Per Square Yard (2016)Cost Per Lane Mile (2016)Total Project Cost Per Lane MileTotal Quantity Completed by Agency in 2016 (Tons/SY)Treatment Placed by Agency or ContractSpecific Treatment Details (gradation, binder type, # of courses, etc.)Pavement Conditions Treated
6
Iowa 7 Uncertain, since recycled pavement is always covered with HMA overlays 155 3.20 213,000 1,090,000 Contract 3-4 inch recycling depth, foamed asphalt stabilizing agent Transverse or block cracking, oxidized pavement
Indiana 8 6-20 6-20